Hi experts,
During the creation of a confirmation time, activity types are filtered by work centre based on the work order instead of based on the work centre reported in the confirmation. This results in an incorrect activity type being provided, showing the synchronisation error "Activity type "x" not defined for cost centre "x".
When reporting a work centre in the order confirmation, the activity type drop-down should update its values to automatically select or change it based on the confirming work centre.
In the backend, the value of the activity type does update automatically based on the work centre.
Thanks!
I would say that you would need to update WO with new work center first prior to work order confirmation.
with that actual costs are reflected correctly on work Order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
13 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.