Skip to Content
avatar image
Former Member

Routing: combination of sequence and overlapping

Dear all,

I have two operations in a sequence. The third operation starts after the two operations before have finished. I would like that the third operation starts when output of the operations before is available, so basically overlapping. But it does not work that both operations from the sequence overlapp with the third one, so the thourghput time is not reduced.

Is overlapping in combination with sequence possible?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 14 at 01:50 PM

    Hi Johann,

    yes it is possible..only for order quantity more than one overlapping settings will

    give you the expected results.

    Check by increasing the production order quantity and logically the machining timinngs should be given

    as the minimum overlap time,say for example assume the machining time for one piece is 20 min

    minutes,so set the same value as the min.overlap time and now check the impact by creating a

    production order for say 10 quantity...

    Please check below transaction for Routing overlapping and sequencing

    http://www.tcodesearch.com/tcodes/search?q=routing+overlapping

    Hope it helps..

    Regards,