on 12-04-2017 10:49 AM
Hi Team,
I have setup classic Kanban for a raw material. I have setup the control cycel for external procurement thru scheduling agreement. The system now shows the kanban bins in "wait" status. I run the Kanban signal and the status changes to "empty" and generates the Schedule Line. I compelte the GR and the status changes to "Full". Now this material is consumed thru production order. The status of kanban does not change to "empty" again. I have to manually change the status.
01. Is there any way by which this issue(CO15-backflush) can automatically reduce the kanban BIN quantity and change the Kanban status at ZERO qty ?
02. Knaban BIN qty is 20 nos and production order consumes from BINs for 2 nos is posted for 261 movt, so balance available qty of this BIN is 18 nos. Where i can see this value ?
Regards,
Dinesh Kumar V.
User | Count |
---|---|
99 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.