I have a rather tricky proplem at the moment. I would need the origin group in the planning layouts for PS planning (CJR2 planning) besides the cost elements (= Seperate Line for the combination of origin groups / cost elements). The wish is to perform a planning by cost element and sub-planning on origin group level ( = material types are classified with origin groups). In Actuals it is possible to create reports including the origin group as well, the only thing we are missing is the planning on this level.

Layout should look like follows:

Cost Element AAAA          Origin Group AAA               Plan Cost Value        

Cost Element AAAA          Origin Group BBB               Plan Cost Value        

Cost Element AAAA          Origin Group CCC               Plan Cost Value        

Cost Element BBBB          ------                                   Plan Cost Value            

Any ideas of how this is possible within the standard ?.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Raimund,

I am searching for the same solution.  I discovered that you can include origin group in ECP planning and in a unit cost estimate created with CJ40 but found no solution for adding the field into CJR2.  Were you able to solve this?

Todd Van Balen

former_member217547
Active Participant
0 Kudos

Hi

You can use value category.

Thanks.