on 08-04-2009 9:18 AM
The transportation calendar in the transportation lane is considered when an ATP check is done in APO (e.g. for a sales order).
Is it possible that more than one transportation calendar (depending on different criteria, e.g. shipping point, shipping condition) can be assigned to a transportation lane?
Hi ael9999,
If you maintain transportation calendar in the transportation lane, it does
scheduling against the means of transport maintained. This works based
on the time stream that you have maintained in customizing.
Other than that if you maintain calendar at the location header level in
transaction /sapapo/loc3, it still does scheduling based on that
calendar for the location.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.