on 08-16-2008 10:26 AM
Dear experts
If you change a APO DP planning book as follows:
- Add two key figures into the planning book (both key figures exist already in the planning area)
- Create one new macro in the same planning book
Would a transport from TEST to PROD such a change require a re-initialization of the planning area and a new activation? I hope not (it is only a view, not the planning area itself).
P.S.: This is a SCM 4.0 system.
Thanks for your feedback,
Eivind
Yes you are correct. Transporting Planning books do not require re-initialization of planning area. you can transport the planning books using /SAPAPO/TSOBJ transaction
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.