cancel
Showing results for 
Search instead for 
Did you mean: 

Extended classic scenario in SRM 7.1

Former Member
0 Kudos

Hi colleagues,

we want top use SRM 7.1 with extended classic scenario and we want to create POs in SRM and reflect them in ERP backend. The question is it possible somehow to change those POs aftewards (e.q. add confirmations, transportation costs, etc...) in ERP? Or is there any way to trasnfer POs in hold status from SRM to ERP and then change them in ERP?

Thanks and regards, Anton

View Entire Topic
Former Member
0 Kudos

Hi Anton,

PO is created a in SRM as local and a copy( copy does not contain the entire PO info, only the useful for the backend) is being sent to R3.

DO NOT try to search a workaround for modification in the backend..sooner or later you will be incurring in incosisnten data and misalignmentes.

SRM is the PO golden source.

Thanks and Regards,

Abraham