Dear Gurus,

We are planning to move into 64-bit platform.

As part of our release strategy we are considering to create a copy EBP, hence 2 SRM pointing at the same time to the same backend system.

Did someone faced before? Any advice would be very appreciated.

Thanks and Regards,

Ab

View Entire Topic
masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

If you can down the system for 2 or 3 days, I recommend simple migration to new H/W. It is low cost and simple.

Regards,

Masa

Former Member
0 Kudos

Solved. Thanks