on 08-05-2017 5:46 AM
Hello All,
I have one query I am not getting exception message 05 (Start date is in past) for a planned order in MD04 for a specific material. The vndoe has RLT of 84 days.
I don't know how RLT and all plays the role in MD04.
Also I don't know much about MD04 dates calculations.
Kindly let me know possible reasons for this.
Also let me know what where should I look into to find the root cause.
Regards,
Sagar
I have attached MD04 and MD12 screenshots also I checked that the scheduling margin key has 15 days of the opening period.So in planned order planned opening date and order start date has 15 days difference. Please let me know what I am missing. Where and how the exception message should appear as " Start date is in past".
Please let me know.
Regards,
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Let me make my statement clear -
If the planned order 'Opening date' is in the past than system current date you will get the exception message '05'
Change the 'Opening date' to 07/08/2017 instead of 09/08/2017 then you will see the exception '05'