How to restrict auto release of a task

SAPSupport
Employee
Employee
0 Kudos

How can I restrict the auto release of a task when releasing the project


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee

Hi Community,

You can implement your own logic controlling whether a task can be released or not in an implementation of BAdI DPR_ATTRIBUTES method IF_EX_DPR_ATTRIBUTES~CHANGE_STATUS_CHECK.

An alternative manual approach would be to ensure that no task type is maintained for the tasks upon creation (note: this also depends on the user setting "Default Values > Task Type"). It is not possible to release a task for which no task type has been maintained. Your users should then only maintain the task type when they are ready to release the task.

Best Regards
Francesco