Hi Gurus,
I am working on RCCP. I have created sales and operations plan on material level. Also, created rough cut planning profile the material and resource combination, entered all values viz. no. of days, base qty, etc.
When I go to MC94 to check rough cut plan and capacity situation, the "Show" option is greyed out. See attached pic "01. SOP view".
Further, I checked some threads on this issue and found that scheduling parameters need to be corrected (OPUZ in may case). However, I don't see the section for rough-cut planning on the said transaction. See attached pic "
02. OPUZ-Sch Parameters" and "03. OPU3-Sch Parameters from another thread"
Can you please suggest what is missing?
Hi Amit,
You can try note 2363798. After having implemented the note it should be possible to define parameters for rough-cut scheduling in OPU4.
Best regards,
Jessica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
10 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.