I have a requirement to procure a material that is serialized in an other plant--MMSL.. the same material is not serialized in ours, Can I still receive it and in future can I transfer it to plants which have a serialization profile on them ?

View Entire Topic
Former Member
0 Kudos

Hi

Yes, You can implement this process.

seriaaizaion nor profile is assigned @ plant and Str leevl

thanks

nagaraj k

Former Member
0 Kudos

Hello NJK,

I understand its assignements, I am more concened about the transactional behaviour in the system.

Former Member
0 Kudos

You apparently can't do that as the profiles need to match.. Moreover the usage shouls always have 03 and cannot be 02.. irrespective you will get an error.. so it is not possible!!