Rework Production Order based on Qunatity Rejected During quality inspection

Expert
Active Contributor
0 Kudos

Is it possible to create the rework production order based on the rework quantity(Material Document) rejected during usage decision ?

Accepted Solutions (1)

Accepted Solutions (1)

Expert
Active Contributor
0 Kudos

As of today, there is no standard functionality, to create rework order automatically. In general - rejected qunatity doesn't only meant to rework, it may be scrap as well.