a month ago
Dear Experts,
I activated Inspection Type 03 for InProcess Inspection and I did the result recording in QA32 for this Inspection Lot and for this operation the result recorded was out of range due to which this lot got rejected so the UD is also rejected but then also confirmation is allowing for next operation and also GR also posted for this Production order by increasing the stock of material. So may I know why its not stopping to do confirmation of next operation if previous operation result recording/UD is Rejected and also why its not stopping to do GR which is updating the stock of this material.
Hello Kiran,
In standard , there is no such validation existing in system where system will restrict the posting 04 inspection lot based on the rejection of 03 inspection type.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Amit_SAP
If result recording of Inspection type 03 lot is rejected, so UD will also reject for inspection type 03 lot. Now if I am doing the UD of Inspection type 04 lot for same material then whether it will stop or is it give any message that Inspection type 03 lot is Rejected so cannot do 04 Inspection lot?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
8 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.