MRP To Generate SCHEDULE LINES for Scheduling Agreement

Former Member
0 Kudos

Hi All,

Please let me know the standard process of how "MRP generating Scheduling Lines for Forecast & JIT"

as well as what all customising do we need to maintain for the same

Regards

Amey Kulkarni

View Entire Topic
Former Member
0 Kudos

hi,

1. Maintain MRP views and forecast view for the material.

2. Maintain Purchase Info Record for the vendor material combination.

3. Create Scheduling agreement.

4. Maintain source list for the material mentioning the scheduling agreement and activate the MRP relevant indicator.

5. Run MRP for the material.

Former Member
0 Kudos

Hi,

Thanks 4 the reply.

Do i need to enter the Delivery schedule in ME38 or system will automatic generate

Regards

amey

Former Member
0 Kudos

Yes schedule lines are automatically genarated.

If you maintain Source list> Material Planning>2 Record relevant to MRP. Sched. lines generated automatically