MRP To Generate SCHEDULE LINES for Scheduling Agreement

Former Member
0 Kudos

Hi All,

Please let me know the standard process of how "MRP generating Scheduling Lines for Forecast & JIT"

as well as what all customising do we need to maintain for the same

Regards

Amey Kulkarni

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

1. Maintain MRP views and forecast view for the material.

2. Maintain Purchase Info Record for the vendor material combination.

3. Create Scheduling agreement.

4. Maintain source list for the material mentioning the scheduling agreement and activate the MRP relevant indicator.

5. Run MRP for the material.

Former Member
0 Kudos

Hi,

Thanks 4 the reply.

Do i need to enter the Delivery schedule in ME38 or system will automatic generate

Regards

amey

Former Member
0 Kudos

Yes schedule lines are automatically genarated.

If you maintain Source list> Material Planning>2 Record relevant to MRP. Sched. lines generated automatically

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)

2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)

3. Create Scheduling agreement using ME31L

4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2

5. During Run MRP for the material.enter the below details.

Processing key NETCH Net Change in Total Horizon

Create purchase req. 1 Purchase requisitions in opening period

Schedule lines 3 Schedule lines

Create MRP list 1 MRP list

Planning mode 1 Determination of Basic Dates for Planned

Depending uopn the demand system will create schedule Lines automatically no need to create manually using ME38.

Rg

Sudhir

Former Member
0 Kudos

`

Former Member
0 Kudos

Dear Sudhir,

Thank you very much for the complete explanation given here. I saw your reply to the thread while googling and found yours to be the best option for my implementation requirement.

rgds...Krishna

Former Member
0 Kudos

At the same time, can you help me with the settings for automatic delivery of these schedule lines to vendor. I meant transmission to vendor through email or net directly..

rgds...KM

former_member824495
Active Contributor
0 Kudos

Hi,

1.Material master MRP views

2.Maintain source list- MRP indicator '2'

3.Maintain Info record

4.Create SA

5.Maintain PIR (planned independent requirement)