on 08-14-2014 9:59 AM
Hi...Gurus .....
My client want the maintenance cost as per the process wise, so can you explain how the cost arriving via the maintenance work order.
i have 3 work centers :- Mechanical, electrical & Tool.
in my Work center i assigned the Cost Center :- Main01 , but in my equipment i assigned the cost center :- Extrusion-01 (Dept cost Center).
how the cost flows from the order .
Hi,
Cost center in work center will calculate the labour cost and post into the order, activity pricing should be made to include the cost.
Cost from various areas like internal / external materials & Internal / external labour will be settled to the equipment cost center, if the equipment cost center is maintained in settlement rule.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lokesh,
If you client wants Process wise cost. You can get it using an Order type. For Example Breakdown Cost, Preventive Cost etc.
If they do not want by Order type, You can use Pm activity type (ILART). For example Mechanical, Electrical etc. (MCI8 Report)
Work Centre Cost: Only to Calculate the cost of activity type (Labor/Machine/Group of people) so that they can be paid accordingly.
Equipment/FL Cost Centre: To calcuate all the cost incurred including activity type cost (WC Cost).
Hope this helps
Thanks and Regards,
Sanjay Tiwari
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.