on 02-04-2009 9:28 AM
Hi,
Is there a table or other ways to download the relationship between materials and operations (results of component assignment) in routing?
Thanks!
Hi Harvey,
Refer to table - PLMZ
If helpful award points
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Harvey,
Table: MAPL - Links material (MATNR) with routing no. (PLNNR)
PLKO - Routing header table (Link with MAPL is via field PLNNR & PLNTY = 'N')
PLPO - Routing operations table (Link with MAPL or PLKO is via PLNNR)
PLMZ - Component allocation link via field PLNNR.
Hope it is clear now, if not do revert back.
If helpful award points
Regards,
Vivek