05-28-2013 6:05 AM
Dear Mentor/s,
I have created one main/superior order in PM and further split it into two sub order. I have received the external service for sub order. The main order value is 150000 and two sub order value is 100000 and 50000. Further i have settled two sub order first and then superior order. When moving to "Cost overview of order hierarchies" , its showing value 300000 and i m fully confused. So, (1) is it right to settle sub order first and then superior order (2) only settle sub order not the superior order.
I have attached screenshot for your necessary review.
Thank in advance for your cooperation.
Regards
Nader
07-04-2013 9:48 AM
Dear Friend,
I think ur confuse with Planned coast and actual coast. Kindly make sure what ur consider.
07-04-2013 9:48 AM
Dear Friend,
I think ur confuse with Planned coast and actual coast. Kindly make sure what ur consider.
07-04-2013 9:48 AM
Dear Friend,
I think ur confuse with Planned coast and actual coast. Kindly make sure what ur consider.
07-08-2013 10:14 AM
No need to be confused because the Superior Order shows the value with the sum of Sub- Orders .You should settle Sub -orders First and then settle superior Order hence your approach is right
It is showing 300000 as a value because Cost for Superior Order and Sub-Orders are added
150000 for Superior Order 4001810+100000 for Order 4001811+50000 for Order 4001812