Buffer in Multiple counter plan

Hi,

In this following link, it is mentioned that Preliminary and follow up buffer is possible in Multiple counter plan.

[http://help.sap.com/saphelp_47x200/helpdata/en/3c/abb35d413911d1893d0000e8323c4f/content.htm]

If it is yes, How buffer can be maintained in IP43 Multiple counter plan ?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on May 04, 2011 at 10:03 AM

    Hi

    You can maintain the same in multiple counter plan scheduling parameter TAB , under Lead float

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 04, 2011 at 10:10 AM

    Hi,

    In Multiple Counter Plan, only Preliminary buffer is allowed.

    In Maintenance Plan Scheduling Parameters, you can find the Lead Float in Days, there you can enter the days. But this is not package level. This is for whole Maintenance Plan.

    In Maintenance Strategy, you can maintain the same in Package level.

    Regards,

    Maheswaran.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.