Buffer in Multiple counter plan

former_member494495
Active Contributor
0 Kudos

Hi,

In this following link, it is mentioned that Preliminary and follow up buffer is possible in Multiple counter plan.

[http://help.sap.com/saphelp_47x200/helpdata/en/3c/abb35d413911d1893d0000e8323c4f/content.htm]

If it is yes, How buffer can be maintained in IP43 Multiple counter plan ?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In Multiple Counter Plan, only Preliminary buffer is allowed.

In Maintenance Plan Scheduling Parameters, you can find the Lead Float in Days, there you can enter the days. But this is not package level. This is for whole Maintenance Plan.

In Maintenance Strategy, you can maintain the same in Package level.

Regards,

Maheswaran.

former_member187991
Active Contributor
0 Kudos

hi

Yes i agree , i think there is a bug or some typing error in the help. as you can see in same link it is specified , OR or AND link can be specified in maintenance plan and package level but you cannot able to see the same at strategy

regards

thyagarajan

Former Member
0 Kudos

Hi,

But even in Maintenance Plan, there is no field for Follow up float. So this may be correct.

Regards,

Maheswaran.

Edited by: Maheswaran.K on May 4, 2011 12:31 PM

former_member187991
Active Contributor
0 Kudos

hi

while defining the cycle set i think there is no hierarchy specified.

can you specify the same

regards

thyagarajan

former_member494495
Active Contributor
0 Kudos

Yes. Premilinary buffer only possible that is through Lead float only

Follow up buffer is not possibe in Multiple counter plan

Thanks to all

Former Member
0 Kudos

Hi,

I feel, Hierarchy & this AND / OR link type are giving same functionality.

For example, there are 3 cycles in Multiple Counter Plan. Monthly, Quarterly & 100 run hours

If OR link type has been maintained, if any of the condition is satisfied, then call object will be created. This is not predictable as Run Hours cant be predicted in advance.

If AND has been maintained, all the conditions should be satisfied.

In Hierarchy also, we can prioritize the frequency, but this predicted one. I am getting confused here.

Please correct me.

But in Cycle defintion, we have no option to maintain that.

shailendradupadhyay
Contributor
0 Kudos

Hi

I think hierarchy can be used for only strategy plan (one dimesional ) but in multicounter plan it wont work thats why AND/OR link is for multicounter plan (Multi dimesional)

Shail

Former Member
0 Kudos

Hi,

I feel, I can open new thread for this discussion instead of continuing this as Alagesan got clarified for his question.

Regards,

Maheswaran.

former_member494495
Active Contributor
0 Kudos

Hierarchy - priority the packages which has the same due date

AND, OR - is to determine when to call the object whether all cycles to reach the cycle or any one

shailendradupadhyay
Contributor
0 Kudos

Hi

Yes Hierarchy is only used to decide which packege to be used if any overllap is there , but AND/OR link is to call the call object upon satisfying the conditions.

Shail

Former Member
0 Kudos

Hi,

In other words, can we say like this?

AND / OR link => To prioritize the conditions given (Which should be satisfied)

Hierarchy => To prioritize the results (To priortize the Package).

But this discussion was really helpful. Thanks.

Regards,

Maheswaran.

former_member494495
Active Contributor
0 Kudos

Yes.

AND, OR - condition of cycles

Thanks to all

former_member187991
Active Contributor
0 Kudos

Hi

You can maintain the same in multiple counter plan scheduling parameter TAB , under Lead float

regards

thyagarajan

former_member494495
Active Contributor
0 Kudos

So, we can't maintain the preliminary and followup in multiple counter plan.

can you explain why P,S entered in multiple counter in the link ?

Lead float is similar to preliminary float

What about followup float ?

Former Member
0 Kudos

Hi,

· S: Maintenance only possible in the maintenance strategy

· P, S: Maintenance possible in both the strategy and the maintenance plan

Scheduling Parameters Single Cycle and Strategy Plan Multiple Counter

Preliminary buffer S S P, S

Follow-up buffer S S

In this, Follow up buffer is not maintained at Maintenance Plan level.

shailendradupadhyay
Contributor
0 Kudos

Hi

Only preliminary Buffer can be maintained in Multicounter plan (Lead float days) , but not the followup buffer.

In that liink also you can find that followup buffer not support for multicounter Plan, only preliminary buffer is allowed in multicounter.

Shail