on 12-13-2018 4:23 AM
Hi,
In Confirmation Parameter ( OPST ) we can activate and define deviation for work and duration. But Is there any Settings In Standard, If I have different Work and/or Duration Deviation depends upon Activity Nature ? Or Should I go for Enhancement ?
Thanks,
Akash Khandelwal
Experts Please help on this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you saying you want to change the Plan Work quantity through a confirmation?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not exactly, Let me explain you in detail;
Standard System behavior as below when Work Deviation active and 5 is entered in Work deviation field.
If I have Activity A with Planned Work of 50 days, 40 days already has been confirmed. Next Confirmation is 15 days, This exceeds the acceptable deviation of 5 percent, will get a warning message.
Same has been applicable to duration Deviation.
Work Deviation and/or Duration Deviation field only allow me to put single value . e.g. 10, 20 etc.. What if , If I have different values depending upon my Project / Activity Nature, Where & How to maintain ?
Thanks,