Dynamic Deviation for Work and Duration at Activity level

akashkhandelwal368
Active Participant
0 Kudos

Hi,

In Confirmation Parameter ( OPST ) we can activate and define deviation for work and duration. But Is there any Settings In Standard, If I have different Work and/or Duration Deviation depends upon Activity Nature ? Or Should I go for Enhancement ?

Thanks,

Akash Khandelwal

akashkhandelwal368
Active Participant
0 Kudos

Hello,

Any one have idea on this ?

Please share.

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

akashkhandelwal368
Active Participant
0 Kudos

Experts Please help on this.

kenmelching
Active Contributor
0 Kudos

Are you saying you want to change the Plan Work quantity through a confirmation?

akashkhandelwal368
Active Participant
0 Kudos

Not exactly, Let me explain you in detail;

Standard System behavior as below when Work Deviation active and 5 is entered in Work deviation field.

If I have Activity A with Planned Work of 50 days, 40 days already has been confirmed. Next Confirmation is 15 days, This exceeds the acceptable deviation of 5 percent, will get a warning message.

Same has been applicable to duration Deviation.

Work Deviation and/or Duration Deviation field only allow me to put single value . e.g. 10, 20 etc.. What if , If I have different values depending upon my Project / Activity Nature, Where & How to maintain ?

Thanks,

akashkhandelwal368
Active Participant
0 Kudos
Ken Melching Waiting for your comment.