Hi,
In production of 10 quantites having 2 operations for example :0010 and 0020. Operations are Partially confirmed in CO11N is this way :operation 0010- 4 quantities( yield) and 0020 - 2 quantities ( yield)
My clients says he wants to postpone the execution of the production order to next week.How to do this? Can it be done in CM21 by dispatching the operations 0010 and 0020 to a different date? But the problem is, it is partially confirmed.
Please suggest some way out.
Thanks and Regards
Hi
f you want to postpone the Operation, so that Remaining available capacity will be utilized by sum other
order, U do TECO to the order, so that remainig capacity u can utilize for other order, when ever u want
to reopen u revoke TECO, and do Capacity leveling in CM21 And proceed further.
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the following link:
http://help.sap.com/saphelp_47x200/helpdata/en/d8/e06a1f7e9c144fbb3a3ed0c38bc38a/frameset.htm
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The production order is partially confirmed so you want to post pone it so you could cancel the production order co13 and again after a week you could confirm it ....
hope this helps you out..
sravanthi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.