Hello,

kindly let me know how to we inout additive costs for any materail to show it in the cost estimate, i have acitivate the update additive costs in the costing varaint.

we want to include the freight costs as addtivie costs and add it to the standarad price of that material,

please let me know ,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188826
Active Contributor
0 Kudos

<b>Step 1</b>

As a first step ensure that in ( OKKN ) valuation variant within the costing variant you are costing has the additive cost check box checked for material valuation. (You need to check against every strategy, if needed). When that priority is picked, where the additive cost is checked, then the additive cost is applied else not.

<b>Step 2</b>

Through CK74N Maintain the additive cost. Enter the the material, the same costing variant and within that screen you can maintain a variable item category. You need to populate the Quantity field,Desctiption, Price-Total, Price Unit, Cost element. (Ensure the cost element in included in the cost component structure under the right head). Save it.

<b>Step 3</b>

Come to CK11N and run the cost estimate for the same material. You can see that besides the value as per strategy, the additive cost is also included.