hi all

main component : x

sub components : y, z

create the BILL OF MATERIAL with quantities 1:1 ration only , means for one main component X , one y and one z need to consume

but when i do GR , for one main component it is consuming 2 quanities of Y and 2 quanities of Z.

could you please give your information to solve this.

Regards,

Rajesh.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi all,

thank very much for your response, we raised issue to SAP.

our team had implemented the note

JL23
Active Contributor
0 Kudos

if you could add the OSS note number then it had even more value to the readers

Former Member

SAP NOTE 2307727

mohsinabbasi007
Active Contributor
0 Kudos

Dear Rajesh,

Waiting for your screenshot of PO Material master Data Tab with Components. Also cross check material master UOM's, is the material has same Base Unit of measure, Order UOM & Unit of Issue.

Best Regards

Mohsin Abbasi

former_member424010
Participant
0 Kudos

Also check for component scrap factor in material master or bom item details. I can't remember if that has an impact during GR but it's worth checking.

JL23
Active Contributor
0 Kudos

Go into your purchase order item detail material tab and take a screenshot after you clicked the components button and post it here for further evaluation