Reg : Updating processing time from routing

81 Views

Dear experts ,

Need few inputs on how system will update the processing time when we execute CA97N transaction.

I have a routing with base quantity 4EA which can be manufactured in 1 hour. ( on Work center -X)

So to produce 1 EA = 15 MIN . But when execute the transaction CA97N i am able to see processing time in work scheduling view it is updates as


18.888 instead of value 15MIN..

How system is calculating the processing time unable to identify. can anyone please clarify me..?

Note : Capacity category = Machine .

Formula in work center = Machine * Operation quantity / Base Quantity/ Operation splits.

Waiting for your valuable inputs..