Hi,

I have made a GR reversal of a subcontrating position. For the main material (not the component), in some of the positions i have no amount in local courrency.


Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

A reversal movement is valuated differently than the receipt, please check OSS note 49995, it is explained with examples.

Your item 7 in the reversal has already a different value than the corresponding receipt item.

I would say you ran out of stock value. SAP cannot reverse more value than you currently have in stock. This is probably caused by the fact that the current moving average is much lower than the PO price

Former Member
0 Kudos

Its true Jürgen. I had quantity, but not value of the stock.

Thanks

Answers (2)

Answers (2)

former_member183424
Active Contributor
0 Kudos

Can you check and post the accounting entry for the reversed document ?

Check what is the difference against others.

Former Member
0 Kudos

hi ,

Can you Please check when you resevered the GR did you ticked Non valuated check box.