Hello Everyone,The issue is, in KKA2, the planned cost is 411169 and in CN41N, CJ41 & S_ALR_87013533 the project planned total cost is 321459. Difference of planned cost in KKA2 & CN41N is 411169 - 321459 = 89710.I found, there is a drop ship PO link...