Dear All,
We are facing some issue with transport, we need to do the transport from DEV 100 client to QAS 200 client, which has been transported in QAS 100 but in the transport route we didn't mentioned QAS 200. So, we are unable to see the TR in the queue.
Kindly suggest me on this.
regards,
Guna
Hi Guna,
If both your development and quality system pointing to the same trans directory (usr/sap/trans), you can add your
transport request manually .
STMS>>Select your System>>Extras>>Add Request.
OR
Go to the history of your development system and try forwarding the request to your destination system.
Hope this helps
Ahamed