on 02-16-2010 11:13 PM
Hi,
We have ECC SNC integration in our project and need to implement customer collaboration ( SNC- Responsive replenishment ( RR) ).
We are using PI 7.1, ECC 6.0 and SNC 7.0.
While I found some links for supplier collaboration but could not find anything useful for customer collaboration Responsive Replenishment.
Can anyone please provide any related doumentation or help on how to proceed with the integration once we have downloaded the standard content.
Regards
Hi,
You have SAP standard content for this. Once you download this from SAP, import them into ESR as those are tpz files. Which will give you all ESR contents and Integration Scenarios. If you dont have any customization requirements, then you need to just configure the Configuration Scenario in the directory like normal (import the Integration Scenario, and rest of the collaboration profiles/agreements)
Btw, while downloading from service market place, you can also download the How to Guide/Master guide which is available there. Not sure did you check this or not ?
just 2 cents, Regards, KM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna,
I have downloaded the standard content for SNC from the service marketplace but could not find any master config guide for the same. Could you please provide me the lnk from where this can be downloaded?
Also, we need to configure the scenarios Responsive Replenishment and SNC ASN Processing but am stuck when trying to configure using the Integration scenarios provided.
Can any one provide the steps that need to be carried out to configure these scenarios?
Any help would be much appreciated.
Regards
User | Count |
---|---|