on 01-31-2014 9:09 AM
Hello Experts,
I'm wondering if there is a way to move Transport Requests (not Transports of Copies) from DEV to Q&A system while the Task List still at 'Development without Release' phase ?
Is it possible at all?
You help will be really appreciated.
Thanks,
MM
HI
Below links discusses the same in standard
Phases in the Project and Maintenance Cycle - SAP Solution Manager - SAP Library
Further, you can either customize the maintenance cycle i.e SMMN to ZMMN etc or switch the phase to Development with Release.
Regards
Prakhar