on 08-16-2007 12:00 PM
I am running process chains early morning. I one process chain I am carry out an attribute change run on 0MAT_PLANT and on the other on different InfoObjects. Can these run at the same time or if they do can they cause a lock? Thanks
Hi Ananad,
you can run at same time.. it's not a problem.. because.. Attribute change run is only applying the new master data or changes of master data in reporting level.. so, it wont give you any cause to lock..
regards
@jay