on 02-23-2009 7:06 AM
Can we do scrap planning in APO ?
We have put the Scrap % in Product Master,but the system is not picking up the same while calculating planned orders during optimiser run.
Kindly give your valuable inputs.
Regards
Guru
Hi Guru,
To maintain itemwise scrap qty, you can define the same in R/3 under mm02 t-code, in MRP1 tab under Lot size data within the field "Assembly scrap(%). Once it is done, carry out the ciffing of location product master data from R/3 to APO so that it gets updated into the PPM
Hope this helps your query.
Please confirm
Regards
R. Senthil Mareeswaran.