on 05-25-2010 2:15 PM
Hi All,
we have maintained 100% quota arrangment for location but system is not completly honouring quota seetings.
we have location P1 and P2 as supplying location and DC1 as dc where inbound quota of 100% from location P1 is maintained. After completion of heuristic we can see that most of the time preq is generated for the location P1(Where quota is maintained) but initial 2 pur req is coming from P2.
master data settings for these two locations are same...transportation time, means of transport etc all are same.
Does any one have faced similar issue? Kindly put down any pointer...
Thanks in advance
Hi ,
Please check Quota valid from date and Transportation lane ( from P1 to DC1) valid from date.
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check OSS note 1260960 u2013 SNP Heuristics Quota Arrangements with lot size if it is applicable.
Secondly , please check if removing quota data for P2 i.e. of 0% quota line in the quota master data , still creates any planned orders for location P2.
If even after removing line item for P2 from the quota master data, Planned orders are created, then please raise an OSS note.
If you are using subcontracting then there are some restrictions and please refer to OSS note 832393 .
We used to have maintaining version-dependent quota master data.
Regards
Datta