Hi Experts,

We have a requirement in Classic scenario:

PRs for MRO / indirect materials generated in PM / PS of ERP will be transferred to SRM using WF interface for approval process.

Upon final approval in SRM, Follow-on document PO should be created in the back end.

The SC in SRM should have the status u201CApprovedu201D & u2018Follow-on Documentu2019 created.

My question is SRM standard will create a PO as follow-on doc after the SC is approved in SRM. How to control this creation of PO in SRM & only approval message should be transferred to back end ERP.

Pls provide any suggestions or inputs on technical settings / adjustments to be carried out.

Note that we cannot use PDP scenario as SRM will be used only for SC approval process.

Tks.

View Entire Topic
former_member183819
Active Contributor
0 Kudos

Hello irahed

According to standard

you are released PR so thats why PRs are turned to SC .

it is valid logically. though you want more validation

in the srm side. you can go for developments

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/5082a622-7310-2c10-1a9b-ef31dd69a...

br