Hi,

What is the term "Parallel Processing" in Meter Reading in SAP ISU?

Usually, we use t.code EL06 or ELEU. What is the difference between EL09 and EL06?

2 REPLIES 2

former_member215295
Contributor

Hi Siva,

Say you want to create meter reading on 10,000 customers,

Instead of running the jobs in a single thread meaning all the customers in 1 bucket say it might take 1 hr.

Instead you create 10 threads each bucket consist of 1000 customers then you can complete the job in 10 minutes, this is what you achieve by parallel runs.

thanks,

Vikram

0 Kudos

Hi

EL06 - only a single job to create meter reading order in one time

EL09 - can create several jobs in one time to create meter reading order

Thanks