on 11-03-2017 9:10 AM
Dear all,
please advise on an issue i am facing with rough-cut capacity planning in SOP. I have created a production plan for material 50133 in plant 2010 (sop.jpg), which i want to run rough-cut capacity planning for. You can see the result of rough-cut capacity planning in the lower part of the screen (i have removed "scheduling" option in OPU4).
My problem is that i do not understand (a) why i see the same capacity requirements for both capacity category 001 (machine) and capacity category 2 (labor hours), and (b) how these values have been derived.
If we have a look in MC35 settings, we will see that my time span is 30 days, and in these 30 days i produce 417300CAR (cartons). I also assume that i can possibly utilize all available capacity of my work center (720hours - 30 days time span * 24 hours/day) (mc35.jpg). Based on these settings, i would expect that for 1568CAR i would need 2,736 hours (720*1568/417300). This value is also verified by the material's routing (standard-values.jpg, machine-capacity-requirements.jpg, all-capacity-requirements.jpg, assigment-of-req-capacity.jpg) and, in addition, no other requirements exist. However, as you can see in the SOP screen, i get very different values from the ones i would expect.
Please advise.
Thank you very much,
Nikos
User | Count |
---|---|
4 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.