Creation of PS WBS Element for selected cProject element

former_member184335
Participant
0 Kudos

Dear Experts,

I have a specific requirement where I am able to create a cProject using the Project Management template from a Portfolio Item. Now from the cProject when I set the status as "Flagged For Transfer" I need WBS elements will be created in a hierarchical manner for cProject definition, phase and tasks underneath.

I have found below nodes, could you please help me that if this is possible using standard configuration ? I have no scope for technical enhancement.

This corresponding structure need to appear in cProject Account tab.

Regards,

AP

Accepted Solutions (1)

Accepted Solutions (1)

judith_gabriel
Contributor
0 Kudos

Dear AP,

you can find information concerning the Accounting Integration process in Wiki space:

https://wiki.scn.sap.com/wiki/display/PLM/Multilevel+Controlling+-+Accounting+Integration+with+Proje...

And also in the Configuration Guide in chapter "Defining Settings for Accounting Integration".

Best regards,

Judith

former_member184335
Participant
0 Kudos

Dear Judith,

Thanks for the help. This wiki linked helped. I am able to perform the manual account integration (if a PS definition already exist). But while I am setting the cProject status to "Flag to Transfer" as per the config a Project Definition and a WBS elements should be created, which is not happening

My requirement is to create WBS element for each Phase and and Task created in cProject. I am getting below warning, will this stopping ?

But the costing variant is present in OKKT also. Account assignment is important for me to perform the scheduling from cProject.

Hope you can help a bit more.

Regards,

AP

former_member184335
Participant
0 Kudos

Dear Judith,

Thanks for the help. This wiki linked helped. I am able to perform the manual account integration (if a PS definition already exist). But while I am setting the cProject status to "Flag to Transfer" as per the config a Project Definition and a WBS elements should be created, which is not happening

My requirement is to create WBS element for each Phase and and Task created in cProject. I am getting below warning, will this stopping ?

But the costing variant is present in OKKT also. Account assignment is important for me to perform the scheduling from cProject.

Hope you can help a bit more.

Regards,

AP

judith_gabriel
Contributor
0 Kudos

Dear Anil,

You can call the controlling cockpit with transaction Cocpcpr in the ERP-system to

receive further information.

Call the following customizing in ERP-system:

spro > Integration with other SAP Components > SAP Portfolio and Project Management >

Project Management > Collaboration Projects > Controlling > Create and Change Controlling Scenario:

Check, if a costing variant is maintained for controlling scenario CPR1.

Best regards,

Judith

former_member184335
Participant
0 Kudos

Dear Judith,

Really grateful for your quick reply. As per your first reply I did all the step (see below).

My PS Project field is blank under Account Assignment tab.

Please note that I used the same coding mask designed in SAP PS. Any further tips ? I am expecting 5 WBS element to be created while changing the status as per the config of Project Type.

Regards,

AP

Former Member
0 Kudos

Hi Anil,

Just inline to what suggested by Judith, please check following SPRO Customizing in PPM Box.

SAP Portfolio and Project Management > Project Management > Connection to External Systems > Accounting Integration > Activate Integration:

For the required Project Type, the scenario should be "A" and Transfer Type = "1".

SAP Portfolio and Project Management > Project Management > Connection to External Systems > Accounting Integration > Define Object Links for Accounting Integration:

For "0FIN_INT_ERP_PS", Destination and Web server details should be correct as per the system landscape.

SAP Portfolio and Project Management > Project Management > Connection to External Systems > Accounting Integration > Make General Settings:

For the required Project Type, the Object type should be "0FIN_INT_ERP_PS" and specify Costing type / Rev. calc. type as per your costing / revenue related configuration.

Also in ERP box, please check following customizing.

Integration with other SAP Components > SAP Portfolio and Project Management >

Project Management > Collaboration Projects > Controlling > Define Controlling Scenario:

For the required Project Type, Controlling method should be "C", CO scenario = "CPR1" and Controlling level = "1".



Hope this helps.



Best regards,

Aditya

former_member184335
Participant
0 Kudos

Dear Aditya,

Thanks for your time and effort, yes this is all maintained as suggested by Judith.

Also I would like to inform you that my ECC and PPM both are in save server, Do i still need to maintain the destination and web server ?

However I am getting below error in COCPCPR. I am maintained the DFM setting for replication but problem is I am not able to add org. Responsible in cProject. This is stopping the PS Project creation.

Will it be possible in standard ? Please note that I do not have HCM implemented.

Regards,

AP

Former Member
0 Kudos

Hi Anil,

As per the error log, it seems that you have a Validation rule that is checking the Person responsible as empty field when project is created and hence fails to create the Project and WBS.

I would request to remove all validation rules or change the error message to warnings in validation steps.

Hope this helps.

Best regards,

Aditya

former_member184335
Participant
0 Kudos

Dear Aditya,

Thanks, my prediction was correct and also you guided properly. I have removed all validation in PS and it has successfully created the PS WBS elements.

Just before closing this thread, I have below concerns;

1. Would it be possible to create WBS elements from cProject using the coding mask defined in PS ? Currently the system created the WBS element with system defined IDs.

2. The system has automatically picked Project Profile as "cProject-PS Integration", is there a config where we can define this profile based on the cProject Template ?

If you suggest I will open a new thread.

Regards,

AP

Former Member
0 Kudos

Hi Anil,

Would suggest to open a new thread.

Best regards,

Aditya

Answers (1)

Answers (1)

former_member184335
Participant
0 Kudos

Thanks Judith and Aditya,

Your valuable inputs helped me to fix the issue.

Closing this Thread. Issue reolved