While doing goods receipt at MB1C,i got the below error:

The description of the error is given below

Valuation area XXX2 not yet productive with material ledger

Message no. C+020

Diagnosis

The material ledger has been activated for the valuation area but material data has not yet been converted in this valuation area.

Procedure for System Administration

If you want to work with the material ledger, choose Accounting -> Controlling -> Actual Costing/Material Ledger -> Utilities -> Production Startup.

There you can convert the data for the material ledger by following the instructions in the online documentation.

Note

Setting the material ledger to productive cannot be undone.

See also:

Actual Costing/Material Ledger in the SAP Library.

The implementation guide for Actual Costing/Material Ledger.

Can you kindly suggest me how to fix this error.

Regards

Sabera

View Entire Topic
Former Member

Hi Sabera,

The Valuation Area is not activated for your material ledger. Go to SAP Access>>Accounting>>Controlling>>product cost controlling>>Actual Costing>>environment>>Production Start up>>Set Valuation area as productive.

If you already activated Valution area in to Productive Statge.

Then go to T.Code OMX1 and for your valuation area XXX2 tick the ML activation box.

the error wont come

regards

srikanth

Former Member
0 Kudos

Hi Srikanth,

Thank you for your inputs. I have solved the problem.

Regards

Sabera

0 Kudos

Hi,

I cannot find below path in S4 HANA.

Could you tell me the path in S4 hana?

Go to SAP Access>>Accounting>>Controlling>>product cost controlling>>Actual Costing>>environment>>Production Start up>>Set Valuation area as productive.

Best Regards.

learner_98
Newcomer
0 Kudos

You can use Transaction code CKMSTART