on 02-18-2008 4:07 PM
Dear Expert,
I have created a new LIS. It works well when I input new data. However, I would like to update my new LIS up to date (data from past until present). Could anyone suggest me how to do it step by step, please?
Thanks,
Prach
Hi,
For updating the LIS with old documents,
you might need to run the following transactions.
OLI7, OLI8 and OLI9.
Hope this helps.
Thanks
Krishna.