Update factory calander

Former Member
0 Kudos

Hi experts.

I'm trying to update factory calander cause its validity date is 2010 only.

How can it be done ??

Thanks in advance,

Rebeka

View Entire Topic
former_member315051
Active Contributor
0 Kudos

You can change the factory calender.

Path: Sales and Distribution - Master Data-Business Partners-Customers-Shipping-Define Customer Calendars-Define Goods Receiving Hours

else you can use T Code : SCAL

Select Factory calender that u want to change and click on pencil icon to change the same.

Former Member
0 Kudos

Hi again.

When I'm trying to update this period I'm getting an error message which tells me that updating is allowed only until 2010.

Thanks all,

Rebeka

aramsum
Active Contributor
0 Kudos

Hi Rebeka,

Please look at the holiday calender associated with the Factory calender . First change (EXTEND) THE Holiday calender and save it. Now try changing the Factory calender. Then It should work.

Regards

Ram Pedarla