Hi All,
I am trying to get table details for getting the earned value (BCWS, BCWP, EAC) data apart from RPSCO table. I would need to report earned value details in Controlling area currency and in object currency.
Can anyone help me in this regard.
thanks
Hi,
Check Table RPSQT.
Check reports CNE1,CNE2,CNE5.
Also for report refer Note 503246 - Check report for the earned value analysis
Check if it can help you.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Yes you are right you also need check COSB. The costs origin are entered in COSP and COSS but during the RA process the systen can check how you recognize you monthly revenues and the adjustment is stored in COSB, but here you only have costs/ revenues adjusted during RA process.
Then you need to check the 3 tables.
Regards