Hi,

While doing set up for Shift Related Confirmation ..

In Confirmation parameters, i could not find Shift / Customer-specific Fields / Subdivision of Quanitities and notification type

I have created Shift Sequence. in Confirmation parameters i have to choose proposal shift. Which i couldn't.

Is there any additional configuration required?

regards

View Entire Topic
Former Member
0 Kudos

Hi,

Thank you

Former Member
0 Kudos

Interesting to note your points awarding method.

Former Member
0 Kudos

Hi,

support package is EHP4.

then also i could not get this functionality.

Pl let me know is there any configuration is required.

Former Member
0 Kudos

Hi,

Follow instructions given in SAP note 1415590 to activate shift-wise confirmation in CO11N.

Regards

Ramakanth

Former Member
0 Kudos

Hi

Thank you.

Solved was problem. I followed as per OSS Note 1415590.

Regards,