on 07-04-2015 8:08 AM
Hi PP experts,
We have a common sub assembly use for different Fert material. But our actual production for different fert is on a different line area in the workshop. So means for the same sub assembly the bom is same but the Routing is different and work center is different. We want to know is there a method that can support us automatic select the right routing during MRP run and create the right production order with right routing and then we can check capacity load with CM01.
Could you please give me some advises? Thank you.
Regards,
Steve
Hello Steve,
There is nothing like right and wrong routing. How system will come to know which one is right routing?
You need to have different production version for your different routing with same BOM. Selection method in MRP 4 view - 2 Selection by production version. Also you can use the Quota Arrangement to plan the particular product on particular assembly line.
Also note in CM21 and CM25 you can select a planned order and change the production version.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.