Requirements date for VSF "backdating" itself in two months

former_member1115366
Active Participant
0 Kudos

Please help me understand this peculiar system behavior.

MD04 routinely displays the plant/materialu2019s planned independent requirement as a u201CVSFu201D having a requirements date of the first work-day of the period. What I cannot explain is why the October 2012 VSF has a requirements date of September 21, 2012. Why would the date not be October 1, 2012? The factory calendar assigned to the plant has October 1, 2012 as a work-day.

Same situation for December 2012. The VSF for December has a requirements date of November 21, 2012.

For the rest of 2012, and for the first three months of 2013, the VSF elements are dated on the first work-day of the month. What would cause the requirements to fall a week and a half early for October and December 2012?

I should add that this peculiarity is not limited to one material. It happens over many materials and across all plants. The common thread among the materials is that we plan them into info structure S608 and then disaggregate among the active warehouses / shipping points.

By the way, I am not very fluent in MRP, so please do not assume that I have ruled out something obvious.

Regards,

zKen

View Entire Topic
ajitkumar
Active Contributor
0 Kudos

pl check your gr processing time for the material

the logic is if the produciton is to happen on 1st oct, the material should be available on 30th sep

if your gr processing time is 10 days, the material should be there in the plant 10 days before

ajitkumar
Active Contributor
0 Kudos

i misread your question.. pl see the folowing link in help.sap

http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2b2b44af11d182b40000e829fbfe/content.htm