Requested delivery date in a Sales Order?

Former Member
0 Kudos

Hi,

In one of my client Functional document, it is mentioned that

[Material Availability Date] = [Requested Delivery Date] u2013 [No days in route]

I want to know that from where does the system get the requested delivery date when we create a sales order?Is it determined automatically based on certain parameters or is defaulted always to the order creation date?

View Entire Topic
Former Member
0 Kudos

It is based on few parameters like

1. The relevant document type and in there Requested Delivery Date and there you will get Lead time in days and you can entar the number of days there. As it Specify the number of days after the current date that the proposal for the requested delivery date in the sales document should be.

2.In material Master MRP2 screen you will get Scheduling Screen where you will get

In-house production

GR processing time

Plnd delivery time