Generate Work Order Preventive Maintenance Automatically

akharisma
Explorer
0 Kudos

Hello..

I have a problem with generating work order automatically in preventive maintenance.
Help me to see where is the problem come from.

This is my tasklist (IA05) :

And this is my measuring point set as a counter (IK01) :

My maintenance plan (IP42) :

My schedule maintenance plan (IP10) and measuring document (IK11) :

As you can see, my question is why my work order generated when the counter doesn't reach the counter level ?

Thank you very much for your help.
Regards,
Agung Kharisma

View Entire Topic
MTerence
Active Contributor

Hi,

Maintain the scheduling of your plan, it was currently displaying as '0'.

Your current measurement reading in 12250.

Now, check the validty from date of Task list, in case if was showing as 22.03.2018, but you are using the start of cycle date in the past, system will try to schedule the plan based on the Task list validity from date. Try to share the screenshot.

Regards

Terence

akharisma
Explorer
0 Kudos

Hello.

This is the task list validity :

Where i can see the start of cycle date ? but i think it doesnt in the past.

Thank you.

Former Member
0 Kudos

Terence got it: "Maintain the scheduling of your plan, it was currently displaying as '0'."

akharisma
Explorer
0 Kudos

Maintain the scheduling of your plan means maintain schedule period in call control parameter ? Is it ?

MTerence
Active Contributor
0 Kudos

Yes, I missed the Period 🙂

Scheduling Period

1. Scheduling Period is not maintained, in such case you will have only the one call which is next.

2. Since your Task list is valid from 21.03.2018, so scheduling will happen from 21.03.2018.

3. If the Start of Cycle date is prior say, 2 years before the current date say 21.03.2016, system created all the orders which are prior to 21.03.2018, so only you are getting multiple orders on single day.

Regards

Terence

akharisma
Explorer
0 Kudos

Ok, i'll try new cycle with schedule period maintained first.

Thank you.

Regards,

Agung Kharisma

MTerence
Active Contributor
0 Kudos

Also, try to create a Task list with a pat validty date like 01.01.2015 and then schedule it.

akharisma
Explorer

Hello Terence,

I already try with schedule period maintained, and it works.
But i have a new question about preventive maintenance, please kindly look my question at this link.

Thank you.
Regards,
Agung Kharisma