TeCo Work Order Preventive Maintenance

Hello...

I want to ask why when i teco my work order with "teco" not "teco with create meas.doc", the last counter reading not recording into "complete counter reading in IP10" ?

Thank you
Regards,
Agung Kharisma

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 03 at 07:28 AM

    Hi,

    Can you please brief your requirement, it will good to shows with screenshots ?

    Completed counter reading will be updated when you complete the Order with the current reading it was.

    When the order was called say it was 2500Hr, but you posted another reading say it become 2550. When you close the order completed counter reading will be 2550.

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

    • Hi..

      When i do it again, the scheme is run normally like the theory that you describe.
      Sorry, iI think there's a misstep a while ago.

      Thank you.
      Regards,
      Agung Kharisma