Hi experts,
I have an issue with scheduling plan dates for call objects in the Maintenance Plan. The call object is notification, Shift factor is 100% and the Completion Requirement is ticked. In this scenario, the notification is a routine alarm.
The routine may not be performed on the planned date. In this case, the notification needs to be closed (Canceled), but the planned date of the next call object should not change (not shift). Is there a standard solution for this?
Regards
Hi,
Dont enter any shift factors (keep it blank), it should create based on the schedule
Regards
Terence