Dear All,                                                                                                                                                              We need to imply the quota arrangement in  MTO process.                                                                             We have maintained below Prerequisites for Quota Arrangements_                                                                    i.e. Vendor Info Record, Source List & Quota Arrangements are maintained.                                                              Splitting Quota Indicator is activated in MRP Lot Sizing Procedure

But after MRP run, purchase requisition are getting created for Single Vendor instead of getting split into vendors as per maintained quota.

Can anyone help in these case.                                                                                                                            Please  Reply 

Thanks   

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In the lot-sizing procedure customizing (OMI4), make sure that the setting Lot Size MTO is set to 2 Lot size as in short-term period, and make sure that splitting quota is set.

Regards,
Caetano 

RajTilak54
Explorer
0 Kudos
Sir @Caetano, have tried the same but its not workable. Thanks