PS questions for a new implementation

Former Member
0 Kudos

Dear Experts,

I am a SAP PS fresher and doing my first implementation project. I have no idea about, what are the 'AS-IS' questions for PS module and also want to know about the 'TO-BE' report for the same. Please-please do help me because my work has completely stop due to this. If possible please provide me 'AS-IS' questions for SAP PS module.

Regards

Aniruddha Mahalle

View Entire Topic
Former Member
0 Kudos

Hi Aniruddha,

In addition to above posts, please also check my reply on below thread

http://scn.sap.com/message/13528385#13528385

Regards

Tushar

sunil_yadav2
Active Contributor
0 Kudos

Dear Tushar,

the link you have mentioned is related to question for certification.

Please provide question which is to be cleared which new implementation from client.

thanks

Sunil

Former Member
0 Kudos

Dear Sunil

Those questions can also act as database for your implementation.

You can also refer following questions.


1. Structure of Projects.
    How client want to structure their projects i.e. only via WBS or only one or several

    network or a combination of WBS & network. Because of functional scope WBS

    that are not assigned to any networks are typically used to map project whose focus

    lies on controlling aspects & so, require very few logistic functions. this kind of projects

    is usually overhead cost or investment projects.


    Again WBS can be structured Phase based structuring , Function based, on Organisation unit.

    Network are predominantly used to map projects in which logistical functions such

    as time scheduling ,resource planning or procurement of materials are required.In the

    combination of both WBS & network we can exploit functional advantages of both.

    When defining structuring the project we should also think like based on which aspect

    client wants to see the data in reporting.If business span across the diff country,.

    You can process Project across Company codes but not Controlling area.

2. Planning :

    Depending upon your requirement,various possibility of time scheduling , how to business is using

    internal & external resource like person, material ( so, we can plan them in activities )

   How much focus is on date planning & Capacity of resource i.e Business project is time critical.

   ( than we have to use network scheduling extensively )

   How they want to plan cost & revenue How they are planning currently project related cost in their

   day to day life. ( so, we can decide which cost planning method will be best suitable to client )

3. For the Cost planning

   First we have to check to FI/ CO how much in depth CO particularly used. Based on that &

    client's requirement for the cost planning we can arrived which type of method to be used. by Cost

    element by date.

4. Revenue planning

    Particularly for the SD project, a revenue planning is important, in order to make assumption

    about the later profits & profitability of project during planning phase.To plan a revenue on WBS

    if SD is there we can plan it on SD documents etc.

5. Budget.
    How Business is controlling budget currently?, What is approval procedure & authority of

    approver etc.

6. Project closing

    In Financial term projects are often serve to collect cost & revenues on only a temporary basis &

    How Business want to that to on which receiver it depends on that.

Regards

Tushar

sunil_yadav2
Active Contributor
0 Kudos

Dear Tushar,

Thanks for these questions. these question will help me in next assignment.

thanks again

Sunil